Prepare for the NCCER Rigging certification exam with these practice questions and answers. This guide covers load calculations, sling selection, rigging hardware, lift planning, and crane signals.

Q: 1) What is meant by the term “two blocking

Answer: The load block contacts the boom point sheaves.

Q: 2) lifting 20,000lbs, with a 2-leg bridle sling at a 30 horizontal sling angle, what is force applied to each leg?

Answer: 20,000

Q: 3) In multiple crane lifts using an equalizer beam, the weight of the beam should be considered:

Answer: Part of the load weight

Q: 4) What is required if there is a deviation in the lift plan?

Answer: A new lift plan

Q: 5) On level ground using skids and rollers, what percent of the weight of the load should yield the required line pull as a general rule of thumb?

Answer: 5%

Q: 6) All of the following are results of unbalanced reeving of the hook block EXCEPT:

Answer: Wear on the hook

Q: 7) Before a spreader bar or beams can be used they MUST have been:

Answer: Tested and approved

Q: 8) When materials are being hoisted to an upper level, a tag line is used to:

Answer: Help control the load

Q: 9) Two cranes are lifting 100 tons . If crane A has 40 % of the load , how much weight will crane B have on its hook?

Answer: 120,000 Ibs.

Q: 10) To confirm the rated capacity of a specific sling, consult the manufacturer’s:

Answer: Sling tag

Q: 11) OSHA regulations require hook replacement if the opening exceeds what percentage of its original throat opening?

Answer: 15%

Q: 12) At what percentage of increase in length should a chain sling be removed from service?

Answer: 5%

Q: 13) The methodical process that attempts to identify hazards and devise plans to overcome or eliminate hazards which may interfere with crane or rigging is called:

Answer: Lift plan

Q: 14) What provides additional control of a load being lifted?

Answer: Tag lines

Q: 15) When traveling on a rubber tire mobile crane, how should the boom be positioned?

Answer: In line with the direction of travel

Q: 16) Before performing pick and carry operations with any mobile crane, it is important to:

Answer: Refer to the manufacturer’s capacity chart

Q: 17 ) According to ASME B30.5 , a two crane lift is signaled by

Answer: One designated person

Q: 18) How much force would be required to move an object up an inclined plane compared to lifting it vertically?

Answer: Less force

Q: 20) All of the following are reasons for stopping personnel lifting operations EXCEPT

Answer: There are no tag lines

Q: 22) The point of any object’s weight can be assumed to be concentrated at:

Answer: Center of gravity

Q: 23) In a spur-gear chain hoist with a two chain system, the endless chain is used to

Answer: Raise and lower the load

Q: 24) In an emergency situation, what is the rigger’s FIRST priority?

Answer: To prevent injury or loss of life

Q: 25) All of the following conditions exert dynamic loading on a crane EXCEPT:

Answer: Static boom angle

Q: 26) Proper lead sheave placement as it relates to the hoisting drum location is:

Answer: Proper spooling of wire rope

Q: 27) The most important information to consider when planning a lift is:

Answer: weight of the load

Q: 28) Prior to use, all new, altered, modified, or repaired rigging hardware shall be inspected by whom?

Answer: designated person

Q: 29) An unsafe condition that riggers should be aware of when dealing with a multi part load block is:

Answer: Twisting multi part lines

Q: 31) The only personnel allowed to have their body parts outside of the suspended personnel platform during hoisting and lowering operations are:

Answer: Signal persons

Q: 32) What is the most important reason rigging hardware should NOT be modified?

Answer: It could negatively affect its capacity

Q: 33) In the term (D/d ratio) the d is an abbreviation for:

Answer: Diameter

Q: 34) A document that outlines weights, crane configuration and rigging requirements for a lift is called a:

Answer: Lift plan

Q: 35) A 1-inch wire rope sling in vertical basket hitch lifting a 24-foot long, 36 inch diameter pipe,

Answer: 36 to 1

Q: 36) What is an LMI?

Answer: Load movement indicator

Q: 37) Location of electrical hazards on the job site should be documented on a:

Answer: Lift plan

Q: 38) When forming a lift plan, a PRIMARY concern for the person doing the rigging is:

Answer: Capacity of rigging

Q: 39) When using a wedge socket, the dead end of the rope is secured in the socket by the:

Answer: Wedge

Q: 40) When erecting or stowing a swing-away lattice extension, what should be used to control the movement of the extension?

Answer: Tag line

Q: 41) Planning for rigging is required:

Answer: Only when lifting any load

Q: 42) A lift plan MUST be completed by a:

Answer: Supervisor

Q: 43) Anchorage points for fall arrest harness for a single person MUST be able to hold:

Answer: 5000 lbs.

Q: 44) Which of the following items are used for heavy rigging?

Answer: Slings, shackles, and spreader beam

Q: 45) If the jacket of a synthetic round sling is damaged, that sling should be:

Answer: Removed from service immediately

Q: 46) Which of the following is NOT a factor when making submerged lifts?

Answer: Water temperature

Q: 47) When a tugger is mounted where the operator can NOT see the load, the signal person most uses

Answer: Signals used for cranes

Q: 48) Who can design a personnel platform?

Answer: A qualified personnel

Q: 49) A one-inch, 3-leg bridle wire rope sling, rigged at a 45 degree angle, is good for 18 tons. The addition of a fourth leg will increase your capacity by:

Answer: 0 lbs

Q: 50) After any structural repair or modification, a personnel lifting platform shall be tested to what percent of the platform rating?

Answer: 150%

Q: 51) All of the following statements about crane contact with power lines are TRUE EXCEPT:

Answer: The operator should leave the cab as quickly as possible

Q: 52) Loads introduced into the machine or its components due to accelerating or decelerating force is called:

Answer: Dynamic loading

Q: 53) Using the sling chart provided, what is the rated capacity of 1/2 wire rope at a choke hitch

Answer: 3,800 lbs

Q: 54) When lifting 100,000 pounds, the main load block must be reeved with how many parts of line?

Answer: 4

Q: 55) What standard hand signal is being communicated in the illustration?

Answer: Travel (one track)

Q: 56) What Standard hand signal is being communicated in the illustration?

Answer: Use whip line

Q: 57) Using the chart, how many parts of line are needed to lift a load weighing 265,000 pounds?

Answer: 9

Q: 57) What is the PRIMARY concern when working with high boom angles?

Answer: Backward stability

Q: 58) On multiple crane lifts, the load on each crane should NOT exceed what percentage of capacity?

Answer: 75%

Q: 59) What are lifting lungs?

Answer: Eyelets welded to a steel plate for lifting

Q: 60)The formula for determining stress on a snatch block performing a vertical lift is: line pull block factor block load. What must be done to calculate the formula?

Answer: Multiply the load weight by the coefficient of friction to determine pull, and then the standard formula

Q: 61) If both fists are placed in front of your body with your thumbs pointed outward, the crane operator should:

Answer: Extend the boom sections

Q: 62) what is the MAXIMUM percent of the rated capacity of a crane that can be used to litft personnel?

Answer: 50%

Q: 63) When does lightening present the greatest hazard to the crane and rigging personnel?

Answer: When thunder and lightning are apparent

Q: 65) Personnel platforms shall NOT be used to lift:

Answer: Tools and materials without employees

Q: 67) When working in close quarters, the main concern is:

Answer: Safety

Q: 64) Most cranes in duty cycle operation require a:

Answer: Load test